Thursday 17 June 2010

site visiting n servicing 1

1. Hartalega
went for software servicing, modify the PLC program of water treatment system.
change the sequence of pump motor opening.

2. KLK - hydrogenation plant
went for cable linking correction. unsuccessful due to wrong drawing given n uncomfirmation of main con.

3. Automatic refinary plant
download new PLC program of new transmitter installation. perform wiring n installment as well.

4. Sime darby refinary plant
loop check, so far havent done due to unwanted bus bar connection.